A major redesign of one of Smiths Falls’ busiest intersections is moving forward, with plans to eliminate the southbound channelized right-turn lane at Beckwith and Lombard streets and make significant pedestrian and accessibility improvements.
Council supported the technically preferred design for the Beckwith Street-Lombard Street-Brockville Street-Jasper Avenue intersection during its Oct. 5 committee of the whole meeting, following a study prompted in part by concerns raised about pedestrian safety and accessibility.
[bsa_pro_ad_space id=11][bsa_pro_ad_space id=8]The preferred design carries a preliminary Class D estimate of $2.05 million, but council did not approve that expenditure Monday night. Instead, Public Works and Utilities Director Paul McMunn was authorized to have TSI Inc. prepare a scope and cost proposal to take the intersection to detailed design. That proposal will return to council before additional engineering work proceeds.
The broader Beckwith Street bridge rehabilitation and intersection project has an approved budget of about $7.35 million, with 90 per cent funded through the Ministry of Transportation’s Connecting Links program and 10 per cent coming from the town.
[bsa_pro_ad_space id=10]McMunn told council there is a “significant delta” between the amount of provincial funding available and the price of the contract already awarded to KB Civil Contractors.
Some work included in the $2.05-million intersection estimate is also already covered by the existing KB Civil contract, he said.
[bsa_pro_ad_space id=12]McMunn said he has spoken with MTO funding officials and the town’s existing transfer-payment agreement allows the funding to be used for engineering and improvements to the intersection.
[bsa_pro_ad_space id=11]“I’m hopeful and confident that there’s enough meat on the bone with the funding that we shouldn’t be out of pocket for much if any of this,” McMunn said.
[bsa_pro_ad_space id=8]He cautioned, however, that he was not making a promise about the final cost to the town.
“We have to work through the detailed design to see where we come in relation to that Class D estimate,” he said.
The preferred design would remove the southbound channelized right-turn lane, realign all four approaches and centre medians, alter several corner radii and upgrade the traffic signals. Proposed accessibility improvements include pedestrian push buttons, audible pedestrian signals and other AODA-compliant infrastructure. Space would also be protected for possible future cycling infrastructure.
The study found sightlines at the existing southbound channelized right turn are limited by the geometry of the bridge approach, the bridge parapet wall and vegetation. The measured sight distance from the pedestrian crossing to southbound traffic coming over the bridge was 54 metres.
Collision data from 2021 to 2025 identified 21 collisions related to the intersection, including four injury collisions. Five collisions involved vulnerable road users, including three in which cyclists were struck by motor vehicles.
The study also examined traffic projections to 2046. Consultant Thomas Brydon of Elements Engineering told council the intersection is expected to continue operating at an acceptable level, although conditions are projected to deteriorate during peak weekend periods.
Coun. Peter McKenna asked whether the proposed investment would provide adequate service for the next 20 years.
Brydon said 20 years is about as far into the future as engineers would want to project traffic conditions because of uncertainty around future residential development, employment and other changes.
The redesign follows concerns raised earlier this year by members of council and the Smiths Falls Accessibility Advisory Committee.
McMunn said the preferred alternative was presented to the committee Sept. 30 and received its support. Committee members said the proposal addresses many of the accessibility and pedestrian safety concerns that led to the study.
Coun. Chris McGuire, who sits on the accessibility committee, said the proposal was well received.
“Very exciting improvements to the corridor,” McGuire said.
He also suggested the detailed design consider landscaping, pavers and other streetscape features used elsewhere on Beckwith Street to provide consistency along the corridor.
Mayor Shawn Pankow said the proposal struck a balance among the competing demands at the intersection.
“I think the outcome is really what we were trying to envision,” he said, calling the preferred alternative “a very practical solution.”
Coun. Jennifer Miller described the result as “quite a relief.”
“We were really in a bit of a pickle this summer looking at this intersection, wondering how we could make it safer and more practical,” she said.
McKenna also acknowledged the role McGuire and the Accessibility Advisory Committee played in pushing for a closer examination of the intersection.
“When I first got the report, I was relatively comfortable with what the first plan was,” McKenna said.
After hearing the concerns raised by McGuire and the committee, he said, “their advocacy was heard” and “really got us to this point.”
McMunn said the town is scheduled to hold a kickoff meeting with KB Civil this week. The contractor has agreed not to begin work on the intersection until next summer, giving the town time to complete the detailed design and provide direction by late spring or early summer 2027.
The $2.05-million Class D estimate is intentionally conservative and will be refined as the design progresses, Brydon told council. It includes such work as asphalt removal, drainage infrastructure, pavement reconstruction, sidewalks, medians and new traffic signals.
CAO Malcolm Morris said staff can work with the consultants during detailed design to identify potential savings and bring the estimate down.
Council supported the staff recommendation to proceed with obtaining the detailed-design scope and cost proposal.
The town is also preparing an application under the next round of MTO Connecting Links funding to examine another intersection.
McMunn said the town intends to seek funding for engineering and analysis of the Union Street-Cornelia Street intersection, including the potential for traffic signals and geometric changes.
Keep connected to your community—read the latest Smiths Falls news.