Confederation Bridge project in Smiths Falls moving ahead despite minor delay

Advertisement
LAURIE WEIR

SMITHS FALLS — The Confederation Bridge replacement project remains on track to finish later this fall, despite harder-than-expected rock slowing excavation, Smiths Falls council heard this week.

Public Works and Utilities Director Paul McMunn reported on Aug. 25 that the old bridge was successfully removed earlier this month.

“It took approximately the whole day to be removed in two sections,” McMunn said. “We cut the bridge in half at the centre pier and removed one side to the east approach, and the other on the west side at Old Mill Road.”

The removal, carried out by subcontractor StructureCraft with Glenview Iron & Metal assisting, required a 150-tonne crane and drew some onlookers.

With the bridge now out, crews are excavating behind the canal wall for new footings and abutments. That work began the week of Aug. 15, though unexpected rock elevations have caused about a half-week delay. McMunn said the project is still expected to wrap up in late October or early November.

The next milestone will be the arrival of the glulam beams, laminated wood arches manufactured in Alberta, in the week beginning Sept. 2. They will be dry-fitted on Old Mill Road before the bridge is lifted into place in a single piece.

“When the time comes, a 500-tonne crane will be set up on the west side at Old Mill Road and Federation Drive to pick up the bridge in its entirety and set it on the new footings,” McMunn said. “That will be a day council may want to attend. It’ll be quite a show.”

The town has commissioned a local photographer, including drone footage, to document the work. McMunn said council will be updated when the bridge components arrive.

Advertisement

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Hot this week

Series of arrests in Smiths Falls: Impaired driver, robbery and violence charges

9-1-1 call results in arrest of impaired driver On September...

Smiths Falls council delays Code of Conduct sanctions against Coun. Quinn

SMITHS FALLS — A decision on whether to suspend...

Police search underway after breach of intermittent sentence in Smiths Falls

Smiths Falls Police issue warrant for 40-year-old male after...

Massive Telus data breach raises privacy concerns in Lanark County

Telus Digital data breach involved about one petabyte of...

Smiths Falls studying potential Alto train station

Consultant preparing business case for a Smiths Falls high-speed...

Smiths Falls council supports recreation facility steering committee

Regional partners may help shape the proposed Smiths Falls...

Smiths Falls council delays decision on business recycling program

Low participation raises questions about the future of the...

Rideau Lakes council moves to coordinate opposition to Alto rail corridor

Bill C-15 concerns and regional outreach shape Rideau Lakes...

Related Articles

Popular Categories