Aging municipal buildings could cost Elizabethtown-Kitley nearly $400K in 2027

Advertisement

Elizabethtown-Kitley could face nearly $400,000 in municipal building repairs and upgrades next year, with aging roofs, failing heating equipment, septic problems and accessibility deficiencies among the concerns identified in a township-wide facilities report.

Building inspector and facilities manager Jason Myre presented the report to the committee of the whole on Oct. 5, outlining completed projects, work underway and improvements that may need to be included in the 2027 capital budget.

[bsa_pro_ad_space id=11][bsa_pro_ad_space id=8]

The Toledo public works garage accounts for $110,000 in proposed repairs, including $40,000 for septic system improvements, $50,000 to insulate and clad deteriorating concrete block walls and $20,000 for heating equipment.

Staff reported repeated septic backups and found that a garage floor drain bypasses the septic tank and discharges directly into the septic field loading area. The tank was in good working order, and the floor drain’s oil and grease separator has been cleaned and serviced.

[bsa_pro_ad_space id=10]

The garage also has six overhead natural gas heaters, although only four are now operational following repairs. Staff believe those units will provide adequate heat through the coming winter.

Advertisement

Another $100,000 is proposed to replace the roof at the Toledo municipal office. Installed in the mid-1990s, the roof has required several repairs over the past two years and is approaching the end of its expected service life.

[bsa_pro_ad_space id=12]

New Dublin fire station faces septic concerns

At Fire Station No. 2 in New Dublin, staff plan to investigate the septic system in spring 2027 after identifying concerns about the slope of the septic bed.

[bsa_pro_ad_space id=11]

According to the report, staff do not know where the existing septic tank is, and pumping maintenance has not been completed.

[bsa_pro_ad_space id=8]

If the system needs upgrading, the work could cost approximately $30,000 because additional fill would be needed. Locating and pumping the tank, along with installing a filter and risers, would cost an estimated $1,500.

The report also raises the possibility of eventually sharing a septic system with a new public works garage.

Another $2,500 has been earmarked for potential masonry repairs at the fire station, where settling has been observed near the front of the building. Staff plan to investigate the brickwork to determine whether additional reinforcement is necessary.

The combined estimate for the fire station is $34,000, proposed for consideration in the 2027 capital budget.

Accessibility improvements also needed

Accessibility deficiencies are another concern across township properties.

The entrance ramp at Spring Valley library does not meet provincial accessibility requirements for slope and landing dimensions. Staff have arranged for engineered drawings and are seeking contractor quotations, with construction anticipated in spring 2027.

The report identifies $50,000 for the ramp improvements, plus $5,000 to replace the library’s deteriorating entrance ceiling.

Advertisement

At Lyn Ball Park, the washrooms also require accessibility improvements, with $50,000 identified for potential upgrades.

Other work is already funded or underway.

A $50,000 decontamination room is being constructed at Fire Station No. 1 in Lyn to provide firefighters with a dedicated area for cleaning potentially contaminated protective equipment. Completion is anticipated by the end of November.

Roof replacement at the Spring Valley library has been delayed until spring 2027 because of scheduling constraints and heavy summer rainfall. The work has been contracted for $39,899.

Improvements to the Toledo library have been completed for $16,931, below the approved $20,800 budget.

The facilities report also addresses work at the former Frankville Public School, where council previously authorized $900,000 for repairs, and outstanding maintenance at the New Dublin municipal office.

The proposed 2027 expenditures have not yet been approved. The committee received the facilities management report at its Oct. 5 meeting, with future spending decisions to be considered through the capital budget process.


Keep connected to your community—read the latest Elizabethtown-Kitley news.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Hot this week

Rideau Lakes council to return to in-person meetings Nov. 15

The Township of Rideau Lakes council and committees will...

Mississippi Mills approves new zoning rules to help farmers diversify

Mississippi Mills farmers looking to expand their businesses beyond...

Bladder health: It’s OK to talk about it

A little leak when you laugh. Another trip to...
Classified Listings

More From This Author

Since when did the word ‘senior’ become a dirty word?

My name is Linda Seccaspina, age 75, and I...

Remembrance Day services across our communities

Communities across Lanark County and Leeds & Grenville will...

Rideau Lakes council to return to in-person meetings Nov. 15

The Township of Rideau Lakes council and committees will...

Mississippi Mills celebrates long-standing businesses at annual appreciation night

The Municipality of Mississippi Mills honoured local businesses, farms...

Perth gathers to honour fallen soldiers on Remembrance Day

Residents of all ages gathered at Perth’s Great War...

Recent Articles

Popular Categories