UPDATE: Nov. 3: Following the committee of the whole discussion, Smiths Falls council approved a heritage alteration permit for demolition of the old water tower, subject to heritage protection, documentation and commemoration conditions. Council deferred awarding the proposed $356,160 demolition contract until the next meting. Any used funds from the approved $400,000 demolition budget are to be directed toward commemorating the historic structure.
The town’s 102-year-old water tower could be gone before Christmas after councillors backed a $356,160 demolition contract Monday night, following a debate over heritage policies and preservation costs.
[bsa_pro_ad_space id=11][bsa_pro_ad_space id=8]During the Nov. 2 committee of the whole meeting, councillors split four to two, with Coun. Jay Brennan absent with prior notice, in favour of proceeding with a heritage alteration permit, despite the Municipal Heritage Committee’s unanimous recommendation for a structural assessment.
The committee subsequently supported awarding the demolition contract to Steric Design & General Contracting, operating as Powertek Construction, of Stittsville.
[bsa_pro_ad_space id=10]Coun. Chris McGuire opposed both recommendations, arguing council was disregarding the heritage policies it adopted earlier this year.
“If we do this with our own personal structure, how can we ask business owners to follow the policy as well?” McGuire asked.
[bsa_pro_ad_space id=12]The tower is a contributing landmark within the Downtown Heritage Conservation District, where demolition is generally restricted except in exceptional circumstances, including structural instability.
[bsa_pro_ad_space id=11]McGuire argued council had not established those circumstances. He said an engineering firm experienced with similar structures had suggested an initial assessment could cost between $5,000 and $30,000.
[bsa_pro_ad_space id=8]“We don’t have the information we need,” he said.
The debate grew pointed when Coun. Dawn Quinn questioned whether an assessment could realistically be completed for $5,000.
“Councillor Quinn, if you came to the Municipal Heritage Committee and filled your seat, you’d know that we got a letter from the engineer signed from a professional that’s done this work across Canada,” McGuire responded.
Quinn pushed back, saying she had sent regrets because of a previous commitment.
“I have been attending meetings. I have heard a lot of this, so I’m really sorry that you feel that I haven’t been at meetings,” she said.
McGuire clarified he was referring to earlier committee discussions.
Quinn maintained her support for demolition.
“I think it’s been a great old structure, but it’s an old structure, and I think it is time for it to come down,” she said.
She also raised liability concerns and supported developing the site into a park area.
Coun. Jennifer Miller favoured further investigation.
“I continue to want an evaluation done before any decision to demolish is made,” she said.
Public works and utilities director Paul McMunn said the town had sought preliminary engineering opinions but had not formally tendered a structural assessment. A comprehensive examination could involve X-rays of riveted joints and corrosion testing, potentially costing substantially more than $30,000.
Retaining the tower could also trigger building code requirements and upgrades involving lead paint and deteriorating steel.
Coun. Peter McKenna supported demolition, citing preservation costs. An earlier rehabilitation estimate was approximately $2.4 million, although the cost of retaining the empty tower as a landmark remains undetermined.
The demolition tender attracted seven bids ranging from $350,000 to approximately $950,000 before HST. Powertek submitted the lowest bid and received the highest evaluation score, earning 93 out of 100.
Council previously approved $400,000 from the Tax Stabilization Reserve, leaving approximately $43,840 after the proposed contract for contingencies and other expenses.
McMunn said the contractor could begin work by mid- to late November and complete demolition within four weeks.
A Heritage Impact Assessment prepared by NPG Planning Solutions acknowledged that demolition would negatively affect the downtown district’s cultural heritage value. It recommended documentation, salvage planning and measures to protect nearby heritage resources.
Chief administrative officer Malcolm Morris said documentation requiring the tower to remain intact would be completed before demolition, with longer-term commemoration to follow.
McGuire criticized the timing, arguing that decisions about salvaging portions of the tower should have preceded the demolition contract. He also questioned why the outgoing council was committing its successor to the project.
“It’s not about burdening the next council with a decision to make,” he said. “The next council’s looking forward to making many decisions.”
The Municipal Heritage Committee meets Nov. 10 to discuss documentation and commemoration. A demolition permit under the Ontario Building Code is still required before removal.
McGuire, Quinn and Miller are all part of the newly-elected council, under mayor-elect Christopher Cummings. New councillors-elect include Bill Dickson, Greg Hull and Alex Brown. The new term of council begins Nov. 15.